The HOA deadline yard
Discovery West · Build May–July 2023
Day one: builder-left grade, cinder fill, and 62 days on the ARC clock.
- Lot7,100 sq ft, 4,050 sq ft of it landscaped
- ScopeGrading and drainage plan, 480 sq ft paver patio, drip and MP-rotator irrigation, 118 plants, low-voltage lighting, ARC submittal packet
- Budget band$48,000 – $57,000
- TimelineDesign 3 weeks · Build 19 working days
The homeowners closed in March with an HOA architectural review deadline and a builder-graded pad that shed water toward the back slider. We rebuilt the finish grade first, cut a swale along the north fence, then set hardscape.
The variable that moved the money
Cinder fill compacted well, so base prep ran under estimate. The savings went into 14 additional shrubs to hit the HOA's planting coverage percentage on the first review rather than the second.